Can I make a filter saying "Data Date + 6M" in P6?

Somprathana TetanunMember for 18 years
Created
6
3
0
I am trying to make 6 Months look ahead filter automatically. But Once I choose the condition DD and try go put + 6M. Then the programme rejects + 6M. How could that be? Because in P3, this filter can be done.

Thanks for all kindly reply.

6 replies

Oldest first
  1. 0
    Ali Farhat ·
    This filter actually works, maybe you wrote the filter wrong.
    The filter should be as follows:
    where "start" "is within the range of" "DD" "DD + 6M"
    if you write "+6M" alone, it will be invalid
    Regards,

  2. 0
    Dieter Wambach ·
    Somprathana Tetanun
    The entry "DD+6m" works exactly the same as in P3.

    Regards and a happy new year!
    Dieter
  3. 0
    Luca Basile ·
    Hi
    you would also want to add the filter for in progress actvities.
    Use the Activity Status field.

    L
  4. 0
    Somprathana Tetanun ·
    Thanks all. I did try again and it works.
    Probably that time the program was error.
  5. 0
    Mi Mo ·

    -

    -

  6. 0
    Zoltan Palffy ·

    works everytime standard item

    works everytime standard item