P6, How Can I Modify Existing Reports Wizards?

Abeer MahmoudMember for 18 years 3 months
Created
5
4
0
At P6, Kindly note that when I modify columns/sort and group at existing reports wizards and save it

I must establish report format again font/header/cells/row titles…etc

How can I avoid this loop?

Regards,
Abeer

5 replies

Oldest first
  1. 0
    Ahmed Elkordy ·
    hello abeer
    if you edit a report using the report canvas you can do ANYTHING and save it....
    but
    if you use the report wizard with a saved report then all that you’ve done using the canvas is lost..
    my advice is....practice using the canvas...it is INFINITELY FLEXIBLE and forget the wizard
  2. 0
    Abeer Mahmoud ·
    Hi Ahmad,

    It is a very good idea I will try it I promise.

    Regards,
    Abeer
  3. 0
    Ardee Tarun ·

    can anyone help me with my

    can anyone help me with my problem. When I copied the projects into cd and as I opened it to another computer, the total duration has  changed and -1 float appeared. How does it happened. By the way, I only did export XER file

  4. 0
    Ferdinand U. ·

    Show time in the dates

    Show time in the dates

  5. 0
    Ferdinand U. ·

    Show time in the dates

    Show time in the dates

Log in or join to reply