How can I have a copy of a P6 file in my protable hard

Ronn Chester BaluyotMember for 18 years 7 months
Created
4
2
0
Is there anyone know how to save a copy of a P6 file into a portable hard disk?

4 replies

Oldest first
  1. 0
    A D ·
    Go to file --> Export and then follow the wizard.

    It will be converted into a .xer file (One single file)

  2. 0
    Ronn Chester Baluyot ·
    Thanks a lot.
    And if I want to open it in a different computer (ofcourse with P6 software), is it as simple as opening an ordinary file?
  3. 0
    A D ·
    Go to File --> Import and follow the wizard. U will have the project into the required EPS

    It’s as simple as export but unlike opening other files by just double-clicking
  4. 0
    Danish Saleem ·
    you can simply Export the file in XAR formate and to save it just give the path to your portable drive.

    Have Funnn....