2 steps queries

Simon HegartyMember for 22 years 3 months
Created
2
3
0


a) Is there a way of creating a global which puts the activity id against each step?

b) Is there a way of flagging up if and when the start or the finish dates of any steps fall outside its parent activity - or is there a setting which ensures that the steps drive the activity date(i suspect not)

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Simon
    You suspected right I’m afraid.
    Steps are not more than a checklist. An activity can’t be finished before all items on this checklist (resp. the steps) are fulfilled.
    You can assign weights and user defined fields to steps, e.g. activity_id, but it will be difficult to use them for a filter. In the table "TASKPROC" you’ll find "task_id" as a foreign key - so it’s automatically assigned.
    You can’t assign a start- or a finish-date to a step. If you’ll require this information, you’ll have to use activities.
    In my opinion a good concept but programming not finalized.

    Regards
    Dieter
  2. 0
    Simon Hegarty ·
    ok thanks for your response