Percent Complete in P3
In the Open Standard
Ali FarhatMember for 17 years 11 months
- Created
- 1
- 3
0
Dear PPs
In P5 and P6 one can not add a percentage completion to any activity without indicating the actual start date...this is logical
however in P3, you add whatever percentage, even 100% complete without having to specify the actual start or finish.
My question is, what adverse effect this has on the schedule (adding 100% complete without actuals)
thanks in advance
In P5 and P6 one can not add a percentage completion to any activity without indicating the actual start date...this is logical
however in P3, you add whatever percentage, even 100% complete without having to specify the actual start or finish.
My question is, what adverse effect this has on the schedule (adding 100% complete without actuals)
thanks in advance
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?