Primavra5 Graphic reports

Mohamed NizamMember for 19 years 7 months
Created
2
2
0
Hello planing enrgr’s can some one help to create graphic reports in P5 as we do in P3 tools>graphic reports. i tried so many times but failed. i want brief explaination.

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Mohammed,
    there are no graphic reports in PM5 as they are in P3
    to display or print a graphic report, open the bottom pane, display the resource profile and enlarge the graph as much as you can
    "Graphic reports" in PM5 are much as Resource profiles in P3
    Hope this helps
    Alexandre
  2. 0
    Xiaobao Lei ·
    Hi,

    Try this method please,

    File -> Print Preview -> page setup -> Options -> JUST tick Profile, UNtick all others -> OK.

    Then you get it.

    Good Luck!