Impact Of Calc Start-To-Start Lag From Actual Start

Olubukola FasoyinMember for 18 years 7 months
Created
4
8
0
Hi Guys,

In P6 there are 2 options in calculating start to start Lag for progressed activities. And this may give different project finish or key milestone dates.

What is best practice. should either of these options be rejected as a client or be contested as a contractor.

Cheers

4 replies

Oldest first
  1. 0
    A D ·
    A lot depends on the project status and also on the agressiveness of the Planning Engr.

    I would prefer to have this calculated using Early Start, as this will give more conservative Schedule but again this will also lead to delay in start of successor.

    Choice is yours!!
  2. 0
    Abdul Khadeer ·
    Gentleman,

    Can you expalin the question and answer as well please.

    thanks
    AK
  3. 0
    Khuong Do ·

    Hi there,I wrote an article

    Hi there,

    I wrote an article to explain these options.

    Kindly read it here https://doduykhuong.com/2020/01/26/primavera-p6-schedule-options-calculate-start-to-start-lag-from/

    Regards,

    Khuong

  4. 0
    Zoltan Palffy ·

    Khuong has the correct

    Khuong has the correct explaination 