Importing P 3.1 (prx.) file to P6.1 (xer.)

Abdul KhadeerMember for 22 years 1 month
Created
3
2
0
Dear all,

Can we import P3.1 (prx.) file to P6.1 without P3.1 installed on our desktop.

I have P6.1 installed on my PC but i get schedules from contractors in prx format. i am facing difficulty in importing.

CAN ANYBODY HELP.

Thanks & Regards
AK

3 replies

Oldest first
  1. 0
    Karim Mahgob ·
    Dear abdul khadeer,

    you don’t need to install p3.1 in your system,,just click on the PRX file to extract it and then go to p6 directly -File menu-import-- choose import from p3
  2. 0
    A D ·
    CHANGE extension from prx to exe and then extract it

    fllow import wizard in p6
  3. 0
    Abdul Khadeer ·
    Thanks Mahgoub & Ravi.

    i got the following error message.

    Type : EOleException

    Event Code : EUERB-2819-3

    Error : Unknown error reported by P3 Engine

    Any solutions Please.

    AK