User Preference Settings in P6

Michael PerryMember for 17 years 6 months
Created
3
3
0
To all

Can you bypass user preference settings for setting number of hours allocated per day

I would like to use the calender assigned to each activity to specify what a day is in hours

I am trying to combine programs with different calendars

Many thank’s in advance

Regards,
Mike Perry

3 replies

Oldest first
  1. 0
    Sandy Matheson ·
    This is a major fault with P5/P6 which I raised with them a long time ago. We also need to use different hours/day calendars due to activities happening in different work areas. Primavera (now swallowed up by Oracle) identified this as an ’improvement’ request which they will consider. But I think probably now forgotten. I have my concerns about what focus Oracle will have on any correction or improvement of the package.
  2. 0
    Saleh Elshobokshi ·
    Primavera promissed that this improvement will be part of next release i.e. P6 ver 7 expected towards end of this year.
  3. 0
    Oliver Melling ·
    Michael,

    The only option that you have is to change the preference settings to hours for duration. This will give the correct durations but is not ideal!