I have accidently over written the following standard report in P6 Report Group Cost: AC-01 Activity Earned Value.

Can anyone let me know what the default columns are supposed to be and what the Group/Sort is.

Thanks

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Kevin,

    First of all, WELCOME to PP.

    Default Columns are the following:

    1. Activity ID
    2. Activity Name
    3. Activity Status
    4. Planned Value Cost
    5. Earned Value Cost
    6. Actual Cost
    7. Budget At Completion
    8. Estimate To Complete
    9. Estimate At Completion Cost
    10. Variance At Completion

    Default Group & Sort:

    1. Total
    2. WBS (with Indent)

    Regards,

    Arnold