User Defined Field

Philip RichardsMember for 22 years 10 months
Created
1
13
0
I have created a user defined field in the ’Activities’Area.

I now wish to pull that field into a Report created under ’Resource Assignments’, but it is not available for selection.

Is there any way User defiened information can be transfered across the two areas.

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Philip,

    I think no. Why not create new UDF using the "Activity Resource Assignments" Field.

    Regards,

    Arnold

Log in or join to reply