project percent complet

Mimoune DjouallahMember for 20 years
Created
10
2
0

I read that there is a workaround to let P6 calculate the total percent complete of schedule when activities are using physical percent complete.

any idea !!

10 replies

Oldest first
  1. 0
    Alex Wong ·

    Hi

    Depends on whether your schedule is resource loaded

    Regards

    Alex
  2. 0
    Mimoune Djouallah ·
    hi alex, yes it is ;)

    thanks in advance
  3. 0
    James Shimmon ·
    Mimoune
    Call up a column called performance % complete, this should mirror physical % complete and will roll up through the WBS levels
    Cheers

    Shimmo
  4. 0
    Mimoune Djouallah ·
    thanks Alex;

    of course the resource must have unit/price assigned, otherwise performance % complete will show always 0
    and to use manhour as a weight factor, we just put price as 1



    mimoune

    note to myself: read the manual before asking questions
  5. 0
    Shahzad Ahmad ·
    Hi Mimoune

    Performance % complete related to cost means price per unit

    if your resource assign only unit...not the cost

    then Performance % Complete will not help.

    Shahzad
  6. 0
    Mimoune Djouallah ·
    Ahmed, that what i want to say, but in mimoune’s english ;)

    thanks very much
  7. 0
    Shanmugam Thangamuthu ·
    Is there any possible way to show project % complete in terms of time / effort like in P3?

    Regards,

    Shan
  8. 0
    Arnold Puy ·
    Hi Mimoune,

    I agree with James, to roll up the percentage based on physical you need to have your performnance % complete equal to your physical % complete. Then, try to change your "% complete type" from duration to physical and observe what will be the outcome.

    This will only work if your programme is cost loaded.

    Just try this exercise and let us know.

    Hope this helps.

    Regards,

    Arnold


  9. 0
    Arnold Puy ·
    Hi Shanmugam,

    In terms of time, you can use "duration % complete".

    Regards.



  10. 0
    Warren Sika ·

    In P3, you will get details

    In P3, you will get details of the project such as the following:

    Number of activities, Number of activities in longest path, Started activities, Completed activities, Number of relationships  and Percent complete.     

    What I am after for is the "Percent Complete". 
     
    My question is, in P6 how will I know its Percent Complete? 
     
    Thanks.
     
    Warren

Log in or join to reply