To have representative Earned Value "S" Curve
In the Open Standard
Brian YungMember for 17 years 7 months
- Created
- 0
- 2
0
Good day gentlemen,
If I would like to have a representative Earned Value Curve in my "activity usage profile", do I have to disable the "recalculate Actual Units and Costs when duration % complete changes" unless I use "physical % complete.
Thanks,
Brian
If I would like to have a representative Earned Value Curve in my "activity usage profile", do I have to disable the "recalculate Actual Units and Costs when duration % complete changes" unless I use "physical % complete.
Thanks,
Brian
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?