working with filter in P6

Aravinth KumarMember for 17 years 7 months
Created
3
3
0
I have the problem while using filter option in p6.

for example :
1. i am creating the user defined filter.
2. i my filter -
parameter = package manager
is = equals
value = some x
3. now when i assign this filter p6 displays me the filtered activities and also other wbs in a collaped manner.

Here how to avoid the display of other collapsed WBS.

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Kumar,

    Not so clear. Cite an example.

    Regards.
  2. 0
    Mark M ·
    Hi Kumar

    If I understand your problem correctly try the following;

    In the activities window, right-click, select group & sort, under the "Group By Options" tick the box "Hide if empty"

    Hope that helps.

    Regards
    Mark
  3. 0
    Aravinth Kumar ·
    thanks mark,

    ya i got it correct when i check the "hide if empty" option.

    regards,
    aravinth kumar.