WBS Milestone Weightage

Haresh JayanthMember for 20 years 2 months
Created
1
15
0
I have done the following steps, for giving weightage for WBS Milestone. Kindly guide me, what i have done is correct or not....

I went to WBS Window and insert a column called " EST Weight" and give Weightage for each WBS.....then use WBS Milestones in performance percentage complete to compute........

Is this a correct procedure....Kindly guide me...

regards,

Haresh

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    That is wrong. Est Weight is used by Top Down Estimation. If you put Est Weight at Activity or WBS and use Top Down Estimation, the units or costs will be distributed according to est weight that specified on Activity or WBS.

    For Earned Value using WBS Milestone Percent Complete is to create a Milestone Step which is similar to activity steps.
    Milestone Step or WBS Milestone is under WBS Window-> WBS Milestone tab.
    Planner needs to create a WBS Milestone step and EV will be calculated according to Milestone steps created.