BL1 curves vs Current Curve

Marc BorburghMember for 22 years 5 months
Created
82
8
0

With the risk of this being asked before, but as excuse that the search ain’t working I’m asking this (apparently) simple question.

I’m working an EPC project at the moment and it’s in P6 6.2

Our schedule got approved by the client and I’ve created the first baseline.

I’ve now progressed the current schedule and want to create a S-Curve showing the Early and Late from the baseline and the actual and forecast from the current (as I used to do in P3).

How is this done in P6??

I’m already very disappointed that I can’t assign percentages to the Y2 axis (if I can, please let me know).

82 replies

Oldest first
  1. 0
    Asyraf Mr ·
    Hi Arnold,

    Please send me a copy at masyrafmr@gmail.com

    Thnx
  2. 0
    Asyraf Mr ·
    Helo Arnold, where are you? really need your help here.

    To all,
    Appreciated if you can email me this doc from Arnold if you got it.
    my email: masyrafmr@gmail.com

    Rgrds,
  3. 0
    Florante Ileto ·
    I hope you can send me a copy too.

    My email add is fdkd2003@yahoo.com

    Thanks
  4. 0
    Arnold Puy ·
    Guys,

    Already sent.

  5. 0
    R. Catalan ·
    Arnold,

    Please send me also at planning_me@yahoo.com

    Best regards,
    R. Catalan
  6. 0
    Arnold Puy ·

    Hi RAlready sent.

    Hi R
    Already sent.
     

  7. 0
    R. Catalan ·
    Thanks a lot Arnold.

    Best regards,
    R. Catalan
  8. 0
    Cleetus Pankiras ·
    Hi Arnold,

    Could please send a copy to my email address mrpcleetus@gmail.com


    Thanks in advance.


    Cleetus
  9. 0
    Brand Rasap ·

    Hi, Please send me also the

    Hi,

    Please send me also the steps in my mail: cubeasice@yahoo.com

    Thanks,

    Brand

  10. 0
    Shah Syed Zaheer ·

    HeyCould you please also

    Hey

    Could you please also kindly send me the steps?
    blue_green@rediffmail.com

    Thanks
    Shahab Bin Syed Zahirudden.
  11. 0
    Muhammad Aqeel ·

    Dear all, Hi Arnold,could

    Dear all,

    Hi Arnold,

    could you please send the  the steps. becoze i'm in very much needed right a way pls

    Regards,

    maqeel
  12. 0
    Mainak Majumdar ·

    Hi Arnold,   Please kindly

    Hi Arnold,

     

    Please kindly send me the steps in my mail ID mainak_moon@yahoo.co.in

    Thanks in advance,

     

    Regards,

     

    Mainak Majumdar

  13. 0
    JW Groeneweg ·

    Hi Arnold,   I am interested

    Hi Arnold,

     

    I am interested in your manual.

    I will send you a pm.

     

    Regards

    Jan

  14. 0
    Weerasaku1 ·

    Dear Arnold,      Please

    Dear Arnold,

         Please kindly send me the step copy regarding this post at weerasaku1@hotmail.com

    Thanks in advance,

    Regards,

    Weerasak

  15. 0
    Ayman Eleish ·

    hope you can send me a copy

    hope you can send me a copy too.

    My email add is ayman_eleish@hotmail.com

    Thanks

  16. 0
    Irfan Khan ·

    Hi, Arnold Sir, Appreciated

     

    Hi, Arnold Sir,


    Appreciated if you can email me a copy of this here irfan_kn2006@hotmail.com

     

    thanks,,,,,

    Irfan Khan

  17. 0
    Luyanda Ndlumbini ·

    Hi Anold can you please send

    Hi Anold

    can you please send me a copy of steps to my email ndlumbinil@yahoo.com

    thanks

    luyanda

     

  18. 0
    Sanad Ahmed ·

    Could you sent me the curv?

    Could you sent me the curv? on :- sanadahmed@yahoo.com

     

    Sanad

  19. 0
    Sanad Ahmed ·

    Could you sent me the curv?

    Could you sent me the curv? on :- sanadahmed@yahoo.com

     

    Sanad

  20. 0
    Sohayle Pasandalan ·

    Hi Arnold, Would you mind

    Hi Arnold,

    Would you mind send me a copy too...

    SPP (psndln@yahoo.com)

  21. 0
    BOULEKHSSAIM Abderrahmane ·

    Hi guys, I mould like to

    Hi guys,

    I mould like to receive it too, ....

    aerski@yahoo.fr

    aerski@gmail.com

    Thansk a lot

  22. 0
    BOULEKHSSAIM Abderrahmane ·

    Dear Arnold , Appreciated if

    Dear Arnold ,


    Appreciated if you can email me a copy of this here aerski@yahoo.fr

     

    thanks.

    Abdou.

  23. 0
    Irfan Khan ·

    hi to all, pls send me this

    hi to all,

     

    pls send me this copy also here      irfan_kn2006@hotmail.com

                                                     irfan_kn2006@yahoo.co.in

     

    i will be thankful forever.

     

    thanks....

  24. 0
    Kumar S ·

    Dear Arnold please send me

    Dear Arnold

    please send me the copy of it.

    satish_sdm@yahoo.co.in

    thanks a lot..

  25. 0
    Kosanhing Ko ·

    Hi Arnold, Would you send me

    Hi Arnold,

    Would you send me the step? kohoihing@gmail.com

  26. 0
    Narayanan Venkat ·

    Can you please send me the

    Can you please send me the same to venkaaat@gmail.com

     

    Thanks

    Venkat

  27. 0
    Kumar Baiju ·

    Hi Dear   Please send me copy

    Hi Dear

      Please send me copy at my email Kbjayswal@yahoo.com, baijukumar@essar.com

     

    Regards\\

     

  28. 0
    Kumar Baiju ·

    Hi Dear   Please send me copy

    Hi Dear

      Please send me copy at my email Kbjayswal@yahoo.com, baijukumar@essar.com

     

    Regards\\

     

  29. 0
    Salah Obaidi ·

    Appreciated if you can email

    Appreciated if you can email me a copy of this here Arnold

    salahedeenobaidi@yahoo.com

    thanx

    Salah

  30. 0
    Evaristus Ujam ·

    Hi, Please send across a copy

    Hi,

    Please send across a copy of this schedule so I can peruse and make my comments. (email: ujamson@yahoo.com.)

     

    Regards.

     

    ujam

  31. 0
    Bert Ella ·

    Sir Arnold,   Please send to

    Sir Arnold,

     

    Please send to my email too. gud_boy_18@yahoo.com

    Thank you in advance.

    Regards,

    Bert

  32. 0
    Mukunda Y ·

    Hi Arnold, Could please send

    Hi Arnold,

    Could please send a copy to my email address  mukunday@gmail.com or mukund.y@rediffmail.com


    Thanks in advance.

    mukunda

Log in or join to reply