Timescale by Year

Nicolas BergerMember for 20 years 4 months
Created
2
2
0
Hi All,

I am working on a multi decades Project so my Timescale is quite extensive.
I need to represent my Resources Usage Profiles on yearly basis and I can’t get that on my P6.2...

I can only get at the maximum by Year/ Quarters. But I want my histograms by year only, how to get to that point ?

On a separate note, How to make a Resource Usage Report like I used to do on P3 on which I used to select My Resources/Costs, the Time distribution criteria such as "day", "week", "month", etc...and then export that as a CSV easy to draw S-Curves on Excel ?

Thanks guys.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Nicolas

    I’m afraid that there is no chance to display on column a year. Even after the timescale was changed to "ordinal" the columns are displayed per quarter - same for the spreadsheet. I wasn’t able to check the ini file.

    Any report you can export as csv-file. For the matrix with the time distributed data you’ll have to mark "Time distributed" in the second window of the wizzard.

    One hint: As you seem to be an experienced P3 user, there is a PDF on your Primavera-dvd: "From P3 to P6". Study this manual before starting with P6.

    Regards
    Dieter
  2. 0
    Nicolas Berger ·
    Thanks for that Dieter !
    Good idea for the Manual on the DVD, I did not know it exists.