Under Admin Preferences, in addition to entering Hours/Day, is entering the Hours/Week, or Hours/Month and,or Hours/Year necessary ? 

As a test case, I entered 8 Hours/Day and 1 Hour/Week and the schedule still seemed fine.

Thanks,

Kashyap Mothali

4 replies

Oldest first
  1. 0
    Amro Ahmed ·

    in most of projects

    in most of projects especially structural

    Hours Per Day :8

    Hours Per Week:40

    Hours Per Month:172

    Hours Per Year: 2000

    Anyway, these rules depend on Work Conditions

  2. 0
    Kashyap Mothali ·

    The question is where are the

    The question is where are the Week, Months or Year data used? If you say 8 hrs/day and yet, set Hours/Week, Month or Year as 1, the schedule is still fine.

    Is it when the schedule is calculated in month, that hours/month come into play? 

     

    Thanks,

     

    Kashyap

  3. 0
    Anoon Iimos ·

    it only means consistency, if

    it only means consistency, if it isn't, then expect otherwise

  4. 0
    Haitham Khaireldin ·

    This is used for the EPS

    This is used for the EPS calculations. Just ignore it and make sure that "Use assigned calendar to specify the number fo work hours for each time period" is checked.

    You can find that option in Admin Preferences---->Time Periods----->under Hours per Time Period