adding bar timescale in P6

Marco FuloMember for 10 years 8 months
Created
4
3
0

Hi All,

Could anyone help me how to add new the timescale of a project made in Primavera 6. I want to show in gantt chart a bar reprensent the Variance between baseline and actual. The bar will start from BL project start to and it will end at Actual start or From BL project finish to Actual finish and also label of Variance BL project duration.

 

Thanks in advance for your help.

Regards,

Marco

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi,Create a UDF Column for

    Hi,

    Create a UDF Column for the dates say Var1 BL Start = BL Project Start, Var1 BL Finish = Actual Start and Var2 BL Start = BL Project Finish, Var2 BL Finish = Actual Finish.

    In the Bar Window, Create a Bar using the UDF dates. Customize with Colors.

     

    Hope this will help.

  2. 0
    Marco Fulo ·

    Hi, Mr. Raymund de

    Hi, Mr. Raymund de Laza,

     

    Greetings...

     

    Thank you so much.. im really appreciated your help... 

    just a little difficulties, i need to enter the dates manually and i have hundreds of activities.

    again thank you...

     

  3. 0
    Raymund de Laza ·

    Use the Global Change....

    Use the Global Change....

  4. 0
    Marco Fulo ·

    Hi, Mr. Raymund de

    Hi, Mr. Raymund de Laza,

     

    Thank you again...