P6, how to create a copy from 20 projects on CD?

Abeer MahmoudMember for 18 years 3 months
Created
7
4
0
P6, I need to create a copy from 20 projects on CD/Directory by a simple way and one step.

Kindly note that your help is urgent.

Regards,
Abeer

7 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Abeer,

    Open all the 10 or 20 projects in Primavera, then go to file export. Follow the wizard. This will create only one file.

    Note: If your project is too big then you need to open 5 or 10 projects at the same time.

    Regards,

    Arnold
  2. 0
    Abeer Mahmoud ·
    Thanks Arnold for your fast reply,

    but kindly note that I need the 20 projects separeat not one project.

    Regards,
    Abeer
  3. 0
    Mohammed Abdul Mazid ·
    hi
    I want P6 Detail version material
  4. 0
    Mohammed Abdul Mazid ·
    hi,
    Before i start working on P6 I want to see the details of P6 will you please provide us the details

    thanks and Best regards
    Mazid
  5. 0
    Arnold Puy ·
    Hi Abeer,

    If you are going to import it back to P6, the 20 projects that you have copied will also equivalent to that numbers.

    However, if you want to copy it separately then I think you have to copy it one by one.

    Regards,

    Arnold
  6. 0
    safinaz ALI ·

    Dear Abeer,Open all the 10 or

    Dear Abeer,

    Open all the 10 or 20 projects in Primavera, then go to file export. Follow the wizard. This will create only one file. 

    when you will use this file you can import any wanted project seprerately from the exported file by shoosing "ignor this project" from the importing wizard this is good way instead of having alot of files.

    Regrds,

    Safinaz

  7. 0
    safinaz ALI ·

    Dear Abeer,Select the 20

    Dear Abeer,

    Select the 20 project, open all (at the same time), then choose "Export" from "File" menue.

    the 20 projects will have small size of MB that will be applicable to be burned on CD.

    Regards,

    Safinaz