Calculated user-defined fields

Rajesh Khanna SakeMember for 20 years 1 month
Created
4
1
0
Is there any way we can insert a user defined column and assign a formula to it to calculate its values in Primavera P6?? I know there is such an option in MSP but I didn’t find one in P6.

Thanks,
Rajesh

4 replies

Oldest first
  1. 0
    Mimoune Djouallah ·
    you have to use global change for that.

    HTH
  2. 0
    Rajesh Khanna Sake ·
    Thank you very much !!!
  3. 0
    Ronald Winter ·
    The web-based P6 has calculated fields but this feature is not in the Client/Server version.
  4. 0
    Rajesh Khanna Sake ·
    I was actually trying to calculate "Calendar Days" - I could assign a formula to the user-defined field and it is working fine at the activity level. But, at the WBS summary level - it is adding up "calendar days" associated with all the activities in that level which I believe is incorrect.
    Is there any way we can change the way the summaries are rolled up just for the user defined fields?

    Many Thanks,
    Rajesh