Percent complete type

Julius AchyMember for 20 years 6 months
Created
2
4
0
Hello Guys,
I am working on n Engineering Project.
The deliverables progress are captured in Excel for onward tranmital to P6. My colleague is asking me to use duration % complete type which I have never use in any of my previous scheduling softwares.
Which is the best % complete type to use in a project and why?
At what time do we use a certain % complete type?

Julius Abuda

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Julius,

    It depends on your requirements:

    1. If you have assign steps to your activities then the best way is to use physical % complete.
    2. If it is resource loaded then unit % complete and physical % complete.
    3. If no resources at all then you can use duration % complete or physical % complete.

    Regards,

    Arnold
  2. 0
    David Wallace ·
    Hi Julius,

    I’ve noticed that this has been posted twice, I’m assuming in error, would you mind if I deleted the other posting?

    Thanks,

    David.