Man Power Histograms in P6

Wael ElhajjMember for 18 years 8 months
Created
1
3
0
Dear All
I am trying to generate a labor histogram on P6, it has worked very fine with the stacked resource selection,yet i still can’t print it...
how is it that graphical reports are generated on P6 as I used to do it in P3

1 reply

Oldest first
  1. 0
    Mervilyne Panganiban ·
    Hi Wael,

    Go to
    1. Print Preview
    2.Page Set up
    3. Look for Options under page set up
    4. Uncheck Activity Table, All Columns and others
    5. then check it...

    Regards,

    Mervilyne