P3e - Budgeted against remaining early units?

Steve BrownMember for 17 years 2 months
Created
2
2
0
Why would the budgeted hours be different to the remaining early units in the resource profile for activities on or just after the data date line? but be the same in activities 3 days out and all future days?

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Steve

    Welcome to PP.

    P3e is a different name for P6 and P5.

    To your question:
    I assume duration type is fixed duration & units.
    For your ongiong activities the reported actual units were less than expected. So within the remaining duration you’ll have to do more work. Due to fixed duration, this has no influence on the remaining duration. All planned activities keep their position.
    Result: Remaining units for the days which follow the data date (i.e. for the ongoing activities) are more than the planned units. Later they are equal again.

    Regards
    Dieter
  2. 0
    Gary Whitehead ·
    moved to p5 / p6 forum