Export Calendars?

Oliver MellingMember for 19 years 5 months
Created
2
2
0
Is it possible to export a calendar so that it can be sent to a sub-contractor via email? (in P5)

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Oliver

    Create a project with one activity per calendar you’ll have to export --> assign the calendar --> Export XER-format. The calendar(s) will be included. Your sub then can import your project and the calendar automatically will be created.
    Pay attention for the names: If a calendar exists with the same name and you have the default settings, that calendar will be skipped and the existing will be used. Maybe you’ll use a prefix with your initials or an abbreviation of your project to provide a unique name.

    Regards
    Dieter
  2. 0
    Oliver Melling ·
    Cheers Dieter.