How to Generate S-curve
- Created
- 83
- 8
83 replies
Oldest first- 0TATanveer Ahmad Niazi ·
Hi Cecil Soliva Sony Lei Mina
Hi
Arnold Puy and
It would be very much appreciated if you send me either the step of how to make S-curve in P6, tanveeraniazi@yahoo.com
Thanx
- 0TATanveer Ahmad Niazi ·
Hi Rafael I don’t have much
Hi Rafael
I don’t have much knowledge of computer setting but have but am receiving mails contain a same word in the beginning or in the middle from different senders. I made a filter with [if the “Subject” “contains” ----- sent to folder ------]. Now all of such mails are coming in to my new folder. This is because some time these mail are from my contacts also that I don’t want the server to block. This may help you.
Thanx
- 0KAKamesh Avasarala ·
dear arnold,i need the step..
dear arnold,
i need the step.. could you pls email to me..
- 0JQJia Qian ·
Dear planers, I am a new
Dear planers,
I am a new scheduler and work for worleyparsons. Could anyone send me the steps how to generate a S-Curve in P6? My email is: qianjiaqian@hotmail.com
thanks a lot!
Jia
- 0JSJorge Santos ·
hi arnold, i have the same
hi arnold,
i have the same problem in p5, i dont how to generate s-curve and dont know how to export in excel.
could u pls. send me the steps.
my email add...jic077c18@yahoo.com
tnx in advance
jorge
- 0NKNaveen Kumar ·
Hi Arnold,Can you send me the
Hi Arnold,
Can you send me the steps to make s-curve percentage in P6?
My e-mail is: vmnaveenkumar@yahoo.com
Best regards,Naveen. - 0AKAhmet K. ·
Hi Arnold, i need also this
Hi Arnold,
i need also this step by step guide to generate S-curve.. Can you pls send me that document too ? Thanks..
- 0IKIrfan Khan ·
Dear Arnold, pls send
- 0RDRaymund de Laza ·
I hope this will help other
I hope this will help other who didn't get the email.
1. Select View>>>Show on Bottom>>> Resource Profile
2. On top of the Bottom right pane select display>> uncheck Show All Projects
3. On the Bottom Right pane>> right click>> Resource Usage Profle Option...
4. Data Tab>> On Display>> Check the check box for Cost >>Check Budgeted under Cumulative>> Apply>>OK
5. On the Bottom left pane>> Select the individual resource you want to show the curve or select all resources to show the Curve of the entire project.
6. Adjust the timescale to show the interval of Time as required. By day.. week.. month .. quarterly.. yearly.. etc..
6. Good Luck!!!
Raymund
- 0MAMarina Azhari ·
Hye. Can anyone kindly send
Hye.
Can anyone kindly send me the steps to make s-curve percentage in P6?
My e-mail is: aki_jr9802@yahoo.comThanks.
Best regards, Marina - 0MLMarjoe Luares ·
Dear Arnold,Can u send me how
Dear Arnold,
Can u send me how to make s-curve (%) in P6 also?
My address: marjoe_092677@yahoo.com
Thank, Marjoe - 0ASAhmad Syahidan Muhamad ·
Hi Arnold, Would you mind
Hi Arnold,
Would you mind to send me too a copy of how to produe S-curve in P6 to syahidan@i-ras.com
thank you - 0ZAZeina Abou Jaoude ·
Hey, Can you please send me
Hey,
Can you please send me the file on how to generate S-Curve in P6 on my email ze_jaoude@hotmail.com ?
I'd be thankful.
Regards.
- 0JIJenny Ingco ·
Dear All,Would you send
Dear All,
Would you send me procedure on how to do S-Curve in P6 on my email hanson_ca76@yahoo.com?
I'd be thankful.
Regards.
- 0ASAnning Sofi ·
P6 will not directly export
P6 will not directly export %ages per time (x-axis) to excel and generate the s-curve from there.
The first post of Arnold is telling you how to export resources; but this is for resource loading per activity only.
P6 will only give you the resource allocation per time (month/week/year) per resource or group or resources, and this will be the basis of you S-curve in excel;
The resource allocation per time is generated thru the reports, or thru the resource assignments tab feature of P6
- 0MDMimoune Djouallah ·
Dear Planners.i just
Dear Planners.
i just uploaded a Excel template for how to generate.
Dynamic S curve.( planned and earned)
Dynamic Summary Progress report.
Dynamic Detailed Progress report.
https://www.box.net/s/ryfxdtnnyhz7qpufgp5l
for the planned value either you import directly from P6, or generate it using the early start and OD, but it is a very simplistic approach, as it suppose the distribution is linear and there is no holidays in the duration of the activity.
in the budget, put whatever you have either manhours or cost, or just value to map your weightage.
the progress is weekly based, you just put the value of the cumulative physical progress in %
and sorry for the hideous Histograms, i am trying to figure out how to change the setting in Excel chart.
hope this help
mimoune - 0ACAdolfo Caccialanza ·
The best solution for
The best solution for Progress Curves Early & late is at this site:
http://www.cla-it.eu/TMSDetails-general.html
Best regards
- 0RSRiyaz Shaik ·
Dear Mr. Arnold,Can you
Dear Mr. Arnold,
Can you please share with me the procedure of Generating S curve in P6.
My Email ID: riyaz.ssits@gmail.com.
Iam new to primavera and I want to generate S curve using pimavera for below scenarion.
Every year we will have many projects(Mechanical,civil,Instrument,etc) and we have to complete the projects on time.Below are the major milestones for each project.
1)Finalizing the scope of work
2)Creating PR
3)Awarding PO
4)Kick off meeting
5)DEP Approval
6)Equipment or Material Delivery
7)Construction
8)Punch list clearnace and System Handover
9)Depreciation and Closeout.
I have to track the completion status of each milestone with respect to time(duration) and I have to report the status of all ongoing projects to our Management.
Please let me know how I can generate S curve by assigning weightage to each milestone with respect to duration of milestone completion.
Your kind support will be highly appreciated.
Thanks in Advance....
Regards,
- 0GWGary Whitehead ·
Arnold, I am aware it has
Arnold,
I am aware it has been 4 or 5 years since you posted on this thread, yet you are still getting requests for you to email.
Could you please advise if you are still sending this stuff out? If not, i shall lock the thread closed.
Thanks,
Gary
Log in or join to reply