Update Actual Dates from other Project(s)

Mah FazelMember for 17 years
Created
2
4
0
Hello
We have Several Subcontractors and get a Plan from each and make the Master Plan.
then every contracor Updates each Plan and we need to update or Master Plan too.
how we can Update Actual dates of our Master Plan from sub contrcactors Updated Plan?
Thanks

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mah,

    Welcome to Planning Planet.

    First of all, you need to create your Master Plan. In order to build the Master Plan as you’ve mentioned in your post by getting all the programmes from the Sub-Contractor and try to import all of these and in the "Import Action" select "Add Into Existing Project".

    During updating, Open your Master Plan and import all the updated programmes of the Sub-Contractor. However, this time in the Import Action, select Update Existing Project".

    Regards,

    Arnold
  2. 0
    Mah Fazel ·
    Hi Arnold
    Thanks for your attention and Reply.
    But the problem is that when Import->Update Existing project, all of Activity parts imported (such as WBS,Pred. & Succ.) but we need to import only "Actual Dates"
    (WBS’s are not same, some of links[pred. and succ.] of Sub-contractors are different from our Master Plan.)
    Is there any way to Set only "Actual Dates" in master plan from Sub contractors updated plan.
    Thanks again!

Log in or join to reply