P6 on Citrix or P6 Web Access

RJ RiveraMember for 22 years 1 month
Created
1
2
0
Hi,

Can anyone give me some opinions on this,
We have been evaluation on which application will we use in providing updates from a remote site to the database(P6).

Can you provide a comparison between P6 Web Access and P6 on Citrix.

Factors that we consider are:
Cost
Stability
Real-time access.


If anyone of you also can provide details how to make citrix running, please send me some info.


Thanks,

1 reply

Oldest first
  1. 0
    David Kelly ·
    Web Tools:

    Only 15,000 activities can be opened at one time
    Only "weekly" resource aggregations, NOT DAILY.

    The above two restrictions prevent most of my clients from using it.

    NO COST TO INSTALL EACH CLIENT!

    Citrix

    Need to teach the remote user all of P6. Huge installation, configuration, training and support costs.

    IF the web client is not too small - go for it.