BUDGET UNITS OVERRIDE ACTUAL UNITS W/ACTUAL FINISH

Jeremy CornerMember for 16 years 11 months
Created
5
2
0
HOW DO I STOP THE BUDGETED UNITS FROM OVERRIDING THE ACTUAL UNITS THAT ARE APPLIED TO AN ACTIVITY? ONLY HAPPENS WHEN I APPLY AN ACTUAL FINISH.

5 replies

Oldest first
  1. 0
    David Kelly ·
    Loads of places you can make it do that!!!!

    In the project tab, check under the "Calculations" tab that "recalculate actual unist an cost when duration % complete changes" is NOT checked.
  2. 0
    Jeremy Corner ·
    David - Thank you. When you say loads of other ways, How else can it be done?
    Thanks again
    JC
  3. 0
    David Kelly ·

    Set the activity to "auto compute actuals"

    Set the resource to "auto compute actuals"


    and there is another one, but I am having a "senior moment", I shall fire P6 up and refresh
  4. 0
    Jeremy Corner ·
    Thanks - You’ve done what our Primavera Rep. and Primavera help line could not do. That was very frustrating for our guys in the field and for me. -Rookie eh-
    JC
  5. 0
    David Kelly ·
    Jeremy,

    I probably have more experience than all of them put together! And that goes for quite a few guys on this forum.