P5 License - New User (NU 1) can’t use

Richard WallMember for 17 years 9 months
Created
3
4
0
I upgraded my license when I had P3e upto P5. I have installed P5. Now when I try open P5 - I type in the default password admin - I get the message License is not valid number of concurrent users is (0). However, my license has New User (NU 1) no expiration date. What can I do now. I have previously had P5 installed on my lap top before as a stand alone. Primavera has always assisted me with the installation in the past as this was a license issue not a maintenance issue. Now Primavera doesn’t seen to want to assist me any longer. Does anyone know how to work around this problem? It appears I have the data bases configured correctly. ??????

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Richard

    Goto Admin --> Users --> select the admin --> tab licensing. Mark "Named User".

    This should be possible even after that error message.

    Regars
    Dieter
  2. 0
    Richard Wall ·
    I can’t open Project Manager to access Admin users
  3. 0
    Dieter Wambach ·
    Richard

    Have a look at your license file - don’t modify, leave editor with "Cancel" or use a copy.

    There you can see the version and the number of licenses and tell it here or use copy&paste. Don’t forget to erase company’s name.

    Regards
    Dieter