Early Start
In the Open Standard
Anbin PonnithMember for 17 years 4 months
- Created
- 3
- 3
0
Hai
I Updated my program as of 6 march&I Schedule it.After Scheduling i saw the Early Start&Early Finsh of Activity 100% Completed & In progress is Calculated From the Data Date,because of it my Successor of the above activity are Getting Delay
I want the Early Start & Early Finish to show me The actcal Dates if its Stated , so that my Successor Activity dates will not get affect.
Is there Any Way to Fix It
Example
Activity ID OD Early start Early Fin Start Finish %
A23R1SA01 22 6-Mar-10 6-Mar-10 14-Feb-10A 2-Mar-10A 100%
A23R1SA02 38 6-Mar-10 9-Mar-10 02-Mar-10A 9-Mar-10 90%
Regard
Anbin Ponnith
I Updated my program as of 6 march&I Schedule it.After Scheduling i saw the Early Start&Early Finsh of Activity 100% Completed & In progress is Calculated From the Data Date,because of it my Successor of the above activity are Getting Delay
I want the Early Start & Early Finish to show me The actcal Dates if its Stated , so that my Successor Activity dates will not get affect.
Is there Any Way to Fix It
Example
Activity ID OD Early start Early Fin Start Finish %
A23R1SA01 22 6-Mar-10 6-Mar-10 14-Feb-10A 2-Mar-10A 100%
A23R1SA02 38 6-Mar-10 9-Mar-10 02-Mar-10A 9-Mar-10 90%
Regard
Anbin Ponnith
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?