Skip to content

Activity Start Date

Arun VasanthMember for 17 years
Created
13
4
0

Dear  friends 

Activity start date and prdecessor finish date are showing sameday  even it is finish to start relation ..

What to do to get the next day as start day in FS relation

Please help 

13 replies

Oldest first
  1. 0
    Kumar S ·

    Dear Arun, You have to check

    Dear Arun,

    You have to check the time period when the first activity has finished .may be the 1st activity has finished earlier then the finish time of the day.

    i mean if you have assigned your calendar timing till 6PM  and your 1st activity has finished at 4pm then the next activity will start immediatly.

    so it is always better to show the hour period in the dates column to get a better idea.

     

    Cheers

  2. 0
    Arun Vasanth ·

    No mine is a day calendor

    No mine is a day calendor 

  3. 0
    Arun Vasanth ·

    no mine is a day calendor

    no mine is a day calendor ...Solution?????

  4. 0
    Alaa Al haj ·

    P6 makes basic calculation

    P6 makes basic calculation based on hours , so it is common to have your problem in schedules

    Solution to your case now as you already prepare the schedule

    To add lag to FS Relation so the activity will start while after predecessor – next day ( NOT BEST SOLUTION)

    Another better solution is – follow below

    • Check first activity start date ( should be first our of activity calendar)
    • Check project / activity calendar ( how many hours per day)
    • If possible make all activity calendar as default calendar  
  5. 0
    D Artagnan ·

    could you have a negative -1

    could you have a negative -1 lag? please check

  6. 0
    Mukunda Y ·

    Dear arun, I faced similar

    Dear arun, 

    I faced similar situations, checl the calender u will get it write.

  7. 0
    Arun Vasanth ·

    Thank you kumar Still I could

    Thank you kumar

    Still I could nt resolve the issue .

    My Activity Calendor is 6 days calendor and it is a day calendor not in hours ..But I put working time period as 10 hrs ...

    My Activity calendor is a six day calendor and project calendor is a 7 day calendor .....

    For Six Day calendor I made the calculation like this 10-60-240-2880.

    And my Project Calendor is a 7 day calendor that is also day calendor .

    Calculation is 10-70-280-3650....

     

    Please resolve my Issue kumar ..

    Any Changes I have to make?????

     

    Regards

    Arun

  8. 0
    Amit Parmar (PMP) ·

    Dear Arun,Goto Edit>User

    Dear Arun,

    Goto Edit>User Preferences>Dates>Time>Choose 24 hours. Then goto the Predecessor activity and check the Finish Date & Time on the activity. The FInish Time should be equal to the Finish time of your Calendar. If it is not thats why the successor is Starting on the same day. This could be due to the following reasons :

    1) The predecessor of the activity has Actual FInish before the end time of Calendar (Change it to Finish time and Re-schedule and it will be fine)

    2) Their is a finish or start constraint and they are After or Before calendar Start Time or FInish Time

    Fixing these time will fix your problem.

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in

  9. 0
    Arun Vasanth ·

    Thank you very much

    Thank you very much dear..

    Atl last resolved by your advice ..

    It took a lot of time to correct all the activities ... then I resolve my head ache .....

     

    Is there any tips to take care for not occur this issue in futre ???????

  10. 0
    Arun Vasanth ·

    Amit Could u review my

     

     

     

    Amit Could u review my below time period calculation??????

  11. 0
    Amit Parmar (PMP) ·

    Hi Arun,What exctly do you

    Hi Arun,

    What exctly do you mean by Time Period calculation? This error usually comes due to 2 reasons :

    1) When we put a constraint and the constraint starts/ends at a different time than the calendar time

    2) When you update your activity and update the % complete to get your Finish Date. You might end up putting a number like 10.2% or 10.6% and Primavera calculates the percentage to the last decimal and finishes the activity on different time than calendar end time.

    To avoid the above problem directly put a finish date on your started activity and Primavera will automatically calculate the % complete and Remaining Duration. It is a much easier and accurate way of getting % Complete (Only if you are using Task Dependent activities)

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in

  12. 0
    Rafael Davila ·

    If you are working on

    If you are working on software that uses hour as the planning unit the following are 3 ways I can suggest for dealing with this issue.

    1. Avoid use fractional days in your durations as to mimic day as your planning unit, the way P3 allowed, this can be very tricky with lag calendars when predefined by a global rule. You might get fractional remaining duration "days" when using % for updating your jobs, watch for this issue if you choose this method.

    2. Use a special calendar for the link that will drive early start of the successor activity along with the successor calendar. For links with lag use double links with nominal successor negative lag. This is easy to do in software that allow for individual links calendars and double links, but harder if not impossible when link calendar is predetermined by a global rule that you can set only within some limits ( P3 falls in the global rule category, not sure about newer versions of P6 ). Do not confuse double links with multiple links even if between same nodes, it is different functionality. If a predecessor SF or FF link can drive the activity then it gets even more complicated.

    3. Use a special calendar for an intermediate milestone that will drive early start of the successor milestone activity and this in turn will drive successor activity along with the successor calendar. This will add a lot of milestones but perhaps this is your only option on software limited at handling link calendars.

    I use a combination of no 1, and no 2 on SS and FS links only on chains where activities have fractional days on their calendar work week.; does not add the additional milestone for every such activity. I recognize the ideal would be 100% no 2 so nothing is manual and the model logic takes due care, but for SF or FF links it gets too complicated for practical use, not to mention double links.

    I believe from the above you can adapt a combination of no 1 and no 3 and still be on a practical approach if option no 2 is not available to you.

  13. 0
    Rafael Davila ·

    Amit,I like your approach to

    Amit,

    I like your approach to use a finish date in Primavera P6 so the software will calculate the remaining duration, it solves the fractional days issue always, good for calendar week with different hours work days. Reminds me of SureTrak "expected finish constraint" that in reality is not considered a constraint but a remaining duration calculator.

    Arun,

    The milestone procedure can be easily adapted to model start of an activity to happen only on certain days of the weeks, say Monday or Tuesday. For all activities considering all link types the milestone procedure and the links calendar it is too complicated to be of practical use, it is more a curiosity. I hope eventually software developers figure it out on a practical way because the need is real.

    At times we have the constraint for activities to start at any AM hour only as PM it is too late to make sense, at times it is the contrary some activities are scheduled to start PM only.

    Seems we got another reason why deterministic CPM schedules are optimistic. In a critical tandem/chain many half days can add significant "unexpected" delay.

    Best regards,

    Rafael

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?