Skip to content

BL,BL1,BL2@% completes in coloumns

Salman AhmedMember for 16 years 7 months
Created
2
2
0
Hi all,

Is there any option in P6 to view Labour Units % Complete of BL, BL1, BL2, BL3 in different coloumns.

I want to see the cummulative % completions of BL1,BL2 (BL1 & BL2 are updated schedules of previous weeks).

Thanks in advance.

2 replies

Oldest first
  1. 0
    Ian Nicholson ·
    Yes, if the baselines are assigned the columns for BL1 (BL2, BL3) Units % complete are available under the percent complete columns.

    Ian

    http://www.emerald-associates.com
  2. 0
    Salman Ahmed ·
    Thanks for your reply,

    I have assigned 2 Baselines Primary & secondary (BL1 & BL2). In the Percent complete coloumn selection view I cannot see the BL2 values.

    Is there any way to view the differences of the % completes from Baselines ( This baseline is secondary BL which is Last week updated schedule) & current schedule so that I can know the weekly progress.

    thanks in advance

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?