about percent completes?

Niles LuoMember for 20 years 10 months
Created
2
2
0
Hi all,
can anybody give me some help about how to calculate the following value in P6.
1, Schedule % Complete for a activity
2, Schedule % Complete for a WBS node
3, performance % Complete for a activity
4, performance % Complete for a WBS node
I want to know the formula, pls give me some reference.
thanks a lot for any help.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi niles
    In P3e there is a nice function: "Hint Help". You can activate it e.g. under View --> Hint Help.
    The information you need you can get under "columns":
    Move the mouse into the table area --> right mouse button --> columns --> expand the group "Percent Complete" --> select the item you want to know by left mouse button --> a window will appear with a correct information e.g. on how this item is calculated.
    Regards
    Dieter
  2. 0
    Niles Luo ·
    Hi Dieter:
    Thanks a lot, I have soluted my questions used the method you provided. Thank you very much.