necking bar for suspended activty in P6??

Lucas lMember for 16 years 7 months
Created
4
2
0
Hello,

Are there any option for necking bar in P6 for suspended activities ?

I have a resource dependent schedule and need to track the budget labour unit closely.

However the nature of the activities I am working on is not continuous. This is extremely conflicting with my P6 setting and my programming logic.

Any advice

Regards

4 replies

Oldest first
  1. 0
    Ian Nicholson ·
    You can neck a suspended bar by going to the bar setup menu, go to the Bar Settings Tab and check the box for Bar Necking for Activity Non-work intervals.

    Ian

    http://www.emerald-associates.com
  2. 0
    Lucas l ·
    Ian, Thanks for your answer.

    For my case, the activity is suspended for multiple time, can that be represented in P6?

    I can only suspend the activity once.

    Regards
    Lucas
  3. 0
    Arnold Puy ·
    Hi Lucas,

    In your case, you can create and assign a calendar identifying all the suspended dates as nonwork.

    Regards,

    Arnold
  4. 0
    Rashid Iqbal ·
    The best way to handle such activities is to split them as the projetc progresses. Change the description as well to indicate the work that actually happened during that period.

    Regards
    Rashid