No Subject Specified
In the Open Standard
Ali FarhatMember for 17 years 11 months
- Created
- 1
- 1
0
In contiguous logic, the FF relation will drive the succ, and the start date will be calculated backward...in other words, the start date of the activity will be determined as finish - duration with no respect to the pred.
Interr vs. Contig. only affects FF relation, by avoiding this type, there will be no diff b/w cont. and inter. logics.
Expected finish cannot be used because dates might change when updating -> expected finish usually distorts the logic.
I agree with Rafael, it is better to split the activity if necessary.
Thanx everyone
Interr vs. Contig. only affects FF relation, by avoiding this type, there will be no diff b/w cont. and inter. logics.
Expected finish cannot be used because dates might change when updating -> expected finish usually distorts the logic.
I agree with Rafael, it is better to split the activity if necessary.
Thanx everyone
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?