Display Single activity per project
In the Open Standard
Vince PeckMember for 16 years 8 months
- Created
- 11
- 3
0
Hello
I have a request from our planning team that they would like to view a layout showing project level with a single activity only ie next task. For example I have a project with five activites and item 1 & 2 are completed 100% so the Planner wants a schedule that shows item 3 only and to exclude items 4&5. Furtermore that due to the volume of projects it would be a ball ache to enter say a % into the next activity.
Any ideas?
Vince
I have a request from our planning team that they would like to view a layout showing project level with a single activity only ie next task. For example I have a project with five activites and item 1 & 2 are completed 100% so the Planner wants a schedule that shows item 3 only and to exclude items 4&5. Furtermore that due to the volume of projects it would be a ball ache to enter say a % into the next activity.
Any ideas?
Vince
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?