User Defined Fields in SDK

Ahmed ElkordyMember for 18 years 3 months
Created
3
4
0
Hello

I’m using the excel sheets that come with SDK to do several things.
I faced a problem, I created user-defined fields for resource assignments on P6 (selling price..etc.), and now I need to "get" them using the excel sheet and input values for them then "set" on primavera.
I tried the "get resource assignemnt UDF" button on the login sheet in the activities workbook but it’s not working.

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Ahmed,
    You need to assign it first before you import using excel sdk. At the moment you just created a UDF field with out data so nothing to import. You can create the values in excel sdk if you know the activity id where to assign them and use set button to update Primavera. You should also run project list first and select the project that you’re going to update.
  2. 0
    Ahmed Elkordy ·
    I did assign one tester resource on Primavera and created the UDF’s, then I tried the get UDF’s button (after I updated project list and selected the project of course), still nothing happened, instead I got an error message.
  3. 0
    Rodel Marasigan ·
    What the error says? Have you use that version of SDK before?

Log in or join to reply