Why is the start / finish dates for LOE tasks differs in primavera generated reports to what’s in the normal bar chart layout ?

Someone please advise.

Thnx in advance
Deepak

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Deepak,
    It depends how you define LOE bar on the Gantt Chart. Is it using the same date as your report?
  2. 0
    Deepak Jain ·
    Thanks Rodel. It is same START / FINISH date in both the Bar chart & in report.
  3. 0
    Rodel Marasigan ·
    Deepak,
    Did you define both LOE Actual and LOE Remaining? or just one of them?