Show impact of planned vs actual resource

Paul GarlandMember for 20 years 9 months
Created
2
2
0
All

I’m trying to demonstrate the impact of a reduced resource on the planned duration of an activity.
The scenario is: an activity was planned to take say 10 hours using 10 men on site (100 man hours) This is the baseline planned duration. In the actual circumstances, only 5 men were allowed on site, so the work takes 20 hours. I want to show this not only in the gantt chart, thus demonstrating the cumulative affect on successor activities, again with less than planned resources but also in the resource histogram. I want to show a resource distribution with the planned and actual either side by side or in total as a stacked bar chart.

Any suggestions?

Paul

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Paul,
    That is easy. Create your baseline first using the 100hrs for 10 men. Use fixed/unit duration type so when adjusting time/unit it will automatically adjust the duration).
    Then Maintain baseline and assigned as Project Baseline.
    Adjust the schedule using 5men for 100hrs. See sample below:
    Resource Impact
  2. 0
    Paul Garland ·
    Thanks

    Paul