Show impact of planned vs actual resource
In the Open Standard
Paul GarlandMember for 20 years 9 months
- Created
- 2
- 2
0
All
I’m trying to demonstrate the impact of a reduced resource on the planned duration of an activity.
The scenario is: an activity was planned to take say 10 hours using 10 men on site (100 man hours) This is the baseline planned duration. In the actual circumstances, only 5 men were allowed on site, so the work takes 20 hours. I want to show this not only in the gantt chart, thus demonstrating the cumulative affect on successor activities, again with less than planned resources but also in the resource histogram. I want to show a resource distribution with the planned and actual either side by side or in total as a stacked bar chart.
Any suggestions?
Paul
I’m trying to demonstrate the impact of a reduced resource on the planned duration of an activity.
The scenario is: an activity was planned to take say 10 hours using 10 men on site (100 man hours) This is the baseline planned duration. In the actual circumstances, only 5 men were allowed on site, so the work takes 20 hours. I want to show this not only in the gantt chart, thus demonstrating the cumulative affect on successor activities, again with less than planned resources but also in the resource histogram. I want to show a resource distribution with the planned and actual either side by side or in total as a stacked bar chart.
Any suggestions?
Paul
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?