Project tab - Summarized data - WBS Level

Haresh JayanthMember for 20 years 1 month
Created
1
3
0
Hi,

If we input at project tab - summarized data to WBS level, and if then summarize at level 2, 3 , or 4 , primavera doesnt summarize the project, what is the use of this function, if no changes is happening on the project level??

regards,


Haresh Jayanth

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    I already answer this to you before; Summarized data to WBS level is for tracking module. It will expand/collapse all projects up to 2 level only if projects are closed and data are being updated when Tools->summarize is run.