Plan Progress vs Actual Progress

Irfan KhanMember for 17 years 3 months
Created
2
1
0
Hi,

What is the difference between Plan Progress vs Actual Progress & how can calculate Variance between this.

thanks.....

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Irfan,
    Plan Progress is taken from your baseline. If you don’t have baseline assigned by default P6 use current Project. Actual Progress is the % complete that you enter every cut-off date before running schedule (F9) on the new Data Date or status date. You can get the variance of the two by showing Column-> Durations-> Variance - Project Duration or Variance – Project Start Date or Variance – Project Finish Date.
  2. 0
    Balaji Surendiran ·
    % Planned : % of works planned to be done (from baseline)
    % Actual: % of actual work happened (you need to update)

    You can insert both the columns and variance as Rodel already explained.

    Regards
    Balaji