Variance between Planned and Actual % complete
In the Open Standard
Cristina BladesMember for 21 years 1 month
- Created
- 6
- 1
0
I am trying to display a column for planned % complete, one for actual % complete and one column for the difference between the 2 in order to show management how far behind each individual deliverable is and also, a certain phase (so it has to roll up to Level 3,2,1). Could you please share your suggestions on how best to display this? i.e. which columns to best use, etc. The project is set up as follows:
*Duration type - Fixed duration and Units/Time
*Percent complete type - Duration
*Activity type - Resource dependent
Thanks in advance,
Cristina
*Duration type - Fixed duration and Units/Time
*Percent complete type - Duration
*Activity type - Resource dependent
Thanks in advance,
Cristina
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?