Global vs Project Calendar Conflicts

Nigel BurnMember for 19 years 2 months
Created
2
1
0
Hi All,
How do the various departments within the company handle the following Calendar issues in Primavera?
1.Projects department require a calendar of 8hrs per day 5 days per week for all FEED office work;
2.Operations require a calendar of 24 hrs per day 7 days per week for TA related work;
Do you set up a global calendar of 24/7 or 8/5?
Do you set the Global calendar to 24/7 or 8/5 and then tell the various departments to use a Project Calendar with the correct hours per day?
Any useful information in solving this issue will be appreciated.
Thanks and Regards.

2 replies

Oldest first
  1. 0
    Joao Ribeiro ·
    If you are using the latest version, define all as global calendars and them use the option to summarize each project according to its own calendar.
    Regards.
  2. 0
    Rodel Marasigan ·
    Nigel,
    Below link is where I explained the use of Multiple Calendar.
    Multiple Calendar Scheduling Post #3
    It may help.