Dear All,

i wanted to export the resource assignmetns for the while project.
but when i am exporting it is showing the resource allacation on hte daily basis. but since i the resource allacation are shift based. i wanted to get the data with respect to the day and night shift.
so please can anybody tell me how to get the resource allcation in hrs on the shift basis..

thank you

4 replies

Oldest first
  1. 0
    Vladimir Liberzon ·
    If you assigned different resources to each shift then daily reports will show each shift assignments in hrs. Just create Resource Breakdown Structure grouping resource by shifts.

    But you know that shift work simulation is not supported by P6. Did you find some workaround?

    Best Regards,
    Vladimir
  2. 0
    Kumar S ·
    Dear,

    I wanted to see the resource loading for the whole project in terms of shifts, ie day and night shift.
    now when i am copying the resource assignment in the excel it is coming on the daily basis only...
    so how to get the resource loading in terms of the total hrs for the shift wise....
    thank you
  3. 0
    Vladimir Liberzon ·
    Dear Kumar,
    did you assign different resources for working in different shifts?
    If yes, then receiving workload reports for resources of each shift you will get necessary information (though not correct).
    It is very easy in Spider Project and I hope that not very hard in P6.

    It is a pity that you work with P6. All your problems do not exist for Spider Project users.

    Best Regards,
    Vladimir
  4. 0
    Rodel Marasigan ·
    Kumar,
    You need to change your Timescale to Day/Shift as date interval and select the Shift Calendar that you used (i.e. TA shift). You should be able to copy and paste to excel or use the report with same timescale saves to csv extension.