rsource assignments
In the Open Standard
Kumar SMember for 16 years 8 months
- Created
- 4
- 2
0
Dear All,
i wanted to export the resource assignmetns for the while project.
but when i am exporting it is showing the resource allacation on hte daily basis. but since i the resource allacation are shift based. i wanted to get the data with respect to the day and night shift.
so please can anybody tell me how to get the resource allcation in hrs on the shift basis..
thank you
i wanted to export the resource assignmetns for the while project.
but when i am exporting it is showing the resource allacation on hte daily basis. but since i the resource allacation are shift based. i wanted to get the data with respect to the day and night shift.
so please can anybody tell me how to get the resource allcation in hrs on the shift basis..
thank you
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?