Remaining Units Late Finish Dates mismatch Finish date
In the Open Standard
Sayat NurabaevMember for 17 years 9 months
- Created
- 5
- 2
0
Hi gents
I am doing a re-baseline of the schedule and come across with a major problem with the remaining units late finish dates. The problem is that finish dates of the early and late units is not the same. I have got an activity finishing on Sep 30 however late finish date shows Nov 7. I can’t understand why it happens. Therefore I can’t generate S-curve as late finish date goes to the wrong finish date.
I seem to have tried all the possible ways, I checked the earned value settings, I checked the resource finish dates on LOE activities. Nothing helped.
Can anyone help me please???!!!
I am doing a re-baseline of the schedule and come across with a major problem with the remaining units late finish dates. The problem is that finish dates of the early and late units is not the same. I have got an activity finishing on Sep 30 however late finish date shows Nov 7. I can’t understand why it happens. Therefore I can’t generate S-curve as late finish date goes to the wrong finish date.
I seem to have tried all the possible ways, I checked the earned value settings, I checked the resource finish dates on LOE activities. Nothing helped.
Can anyone help me please???!!!
5 replies
Oldest firstLog in or join to reply