Data Date
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 2
- 1
0
Dear Planners,
Is data date in P6 different from data date in P3?
I mean in P3, if the activity duration is 4 days and 75% completed after 2 days, the data date is the second day which will lead to one day remaining.
In P6, the data date should be the third day to lead to one day remaining.
Regards,
Moutaz
Is data date in P6 different from data date in P3?
I mean in P3, if the activity duration is 4 days and 75% completed after 2 days, the data date is the second day which will lead to one day remaining.
In P6, the data date should be the third day to lead to one day remaining.
Regards,
Moutaz
2 replies
Oldest firstLog in or join to reply