Activity Count Issues while using filter

Shah. HBMember for 17 years 10 months
Created
3
2
0
Hi to all

Is there any option in P6, to count number of activities present in the current layout after application of user defined filters?

3 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Shahul

    Just copy paste the task names to excell.

    Best regards

    Mike Testro
  2. 0
    Rodel Marasigan ·
    Shahul,
    Yes P6 has an option to count activities shown on the layout. (Right click on activity window and select Column-> Number of Activities-> Activity Count)
  3. 0
    Shah. HB ·
    \Many thanks

    Mike & Rodel