Hello Planners,
I’m hoping that I have made a simple error somewhere with my calculations that can solve my current mystery.
Presently I have a plan that is progressing; the budget is set and measured as a maintained project BL.
To measure monthly update variances I maintain and assign a further baseline of the current project to the plan. When I assign the current project as BL1 I am getting a variance in the BL1 total cost - At completion total cost.
Why does the BL1 Total cost (of either assigned current project or a maintained BL of the current project) not equal At completion total cost for the project?
Your assistance is greatly appreciated.
Kind regards
Robin.
I’m hoping that I have made a simple error somewhere with my calculations that can solve my current mystery.
Presently I have a plan that is progressing; the budget is set and measured as a maintained project BL.
To measure monthly update variances I maintain and assign a further baseline of the current project to the plan. When I assign the current project as BL1 I am getting a variance in the BL1 total cost - At completion total cost.
Why does the BL1 Total cost (of either assigned current project or a maintained BL of the current project) not equal At completion total cost for the project?
Your assistance is greatly appreciated.
Kind regards
Robin.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?