Planning Forecast data

Shazia khanMember for 18 years 5 months
Created
1
2
0
Greeting!!

Dear Sir Mr. Rodel

I am working on a Bid Schedule, in that Planning ensure all progress and Forecast planning data
(Cost And Man-Hours)

Please advise me how to set manually forecast Planning Data,

for Cost and Man-Hours,

there is any calculation or roule to calculate forecast, data.

Best Regards

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Shazia,
    You can use future bucket to spread your cost and man-hour data. Make sure unit/time is set so using hour can have automatic cost.

    If you wanted to separate cost and hour then you have to un-tick calculate cost from units.

    Best Regards,
    Rodel